Approximate
Week of:
|
Contractor
|
Buyer
|
Item
|
|
|
12/1
|
x
|
|
Strip topsoil
|
|
12/1
|
x
|
|
Layout final location of house
|
|
12/1
|
|
x
|
Select color (exterior) of windows.
|
|
12/1
|
|
x
|
Select shingles: style and color.
|
|
12/1
|
|
x
|
Select siding: style and color
|
|
12/1
|
|
x
|
Select brick style.
|
|
12/7
|
|
x
|
Select fireplace, type of mantel, hearth size
and weather raised or flush with floor. |
|
12/7
|
x
|
|
Excavate basement, pour footing, install interior sub slab
drainage and stone.
|
|
12/14
|
|
x
|
Kitchen and vanity cabinet style and arrangement including
tops and bowls (must have before roof framing starts).
|
|
12/14
|
x
|
|
Form wall and pour concrete.
|
|
12/14
|
|
x
|
Determine location and size of any recess in wall for medicine
cabinets, etc.
|
|
12/14
|
|
x
|
Select color of bathtubs, whirlpool and model
if different than specified (must have before first floor deck is complete) |
|
12/14
|
|
x
|
Select areas that will have vinyl, wood, &
ceramic |
|
12/21
|
x
|
|
Backfill foundation and stone driveway.
|
|
12/21
|
x
|
|
Wood framing starts |
|
1/14
|
x
|
|
Install exterior windows and doors |
|
1/21
|
x
|
|
Install shingles |
|
1/21
|
x
|
|
Install brick |
|
1/21
|
x
|
|
Pour concrete basement, garage, patio, front
porch floors. (weather permitting) |
|
1/21
|
x
|
|
Rough heating starts, central vacuum rough in, if
applicable |
|
1/21
|
x
|
|
Rough plumbing starts |
|
1/28
|
x
|
|
Install sliding |
|
1/28
|
|
x
|
TV, Phones, and meet with electrician, rough
wiring starts |
|
2/5
|
|
x
|
Select faucet, sink, towel bars, tissue holder |
|
2/5
|
|
x
|
Select vinyl, hardwood, ceramic, carpeting, selections,
etc. |
|
NA
|
|
x
|
Security if applicable |
|
NA
|
|
x
|
Intercom and audio/visual system rough in, if
applicable |
|
2/5
|
|
|
Select finish paint (walls & ceiling; interior
wood trim; windows & doors; exterior doors that are to be painted) |
|
2/5
|
x
|
|
Install insulation |
|
2/12
|
x
|
|
Install and finish sheetrock (drywall) |
|
2/12
|
|
x
|
Select door hardware |
|
2/12
|
|
x
|
Select glass and frames for shower and tub enclosures |
|
2/19
|
x
|
|
Install vinyl |
|
2/19
|
x
|
|
Interior trim and doors installed |
|
2/19
|
x
|
|
Install tile work |
|
2/19
|
x
|
|
Painting & Staining begins |
|
|
x
|
|
Rough hardwood installed, if applicable |
|
2/26
|
x
|
|
Finish heating and a.c. systems |
|
3/10
|
x
|
|
Kitchen and vanity cabinets and countertops installed |
|
3/17
|
x
|
|
Install receptacles and switches, assemble and
install light fixtures |
|
3/17
|
x
|
|
Install plumbing fixtures (faucets, toilets,
sinks, etc.) |
|
3/25
|
x
|
|
Install sidewalk & driveway (weather permitting) |
|
3/25
|
x
|
|
Sand, stain (if applicable) and finish hardwood
floors |
|
NA
|
x OR x
|
Finish security, audio/visual and
intercom, if applicable |
|
3/25
|
x
|
|
Install tub and shower doors and vanity mirrors |
|
3/25
|
x
|
|
Install carpet and remainder of floor covering |
|
3/25
|
x
|
|
Install windows screens and grilles, if applicable |
|
NA
|
x
|
|
Install deck, if applicable. (weather permitting) |
|
NA
|
x
|
|
Landscape, if applicable. (weather permitting) |
|
NA
|
x
|
|
Rake and seed lawn. (weather permitting) |
|